Installation of the geothermal loop
Foundation work performed by Fondasol for cementing job following
|
August 2007 |
|
Installation of the geothermal loop
Preparation of the platform to build the geothermal loop and the ORC power plant
|
September 2007 |
|
Installation of the geothermal loop
Reception of five Heat exchangers (Barriquand)
|
September 2007 |
|
Installation of the geothermal loop
Platform preparation (Company Leon)
|
October 2007 |
|
Installation of ORC power plant
Installation of the air cooling system (Turboden)
|
November 2007 |
|
Installation of ORC power plant
Installation asynchronous Generator 1,5MW
|
December 2007 |
|
Installation of ORC power plant
Installation radial turbine 1,5MW (Cryostar)
|
December 2007 |
|
Installation of geothermal loop
Air cooling system (Ormat)
|
January 2008 |
|
Installation of geothermal loop
Self-cleaning filter, (Poutet, Lefco, 50μm and 150μm)
|
February 2008 |
|
Installation of geothermal loop
Installing Pipes to connect heatexchanger with cooling system and wells (Stib Company)
|
April 2008 |
|
Installation of geothermal loop
Installation of actuators and sensors, automatisation (SOVEC)
|
Mai 2008 |
|
Installation of ORC power plant
Filling of Isobutane into ORC working fluid system
|
Mai 2008 |
|
Start of Production of electrical power
Visit of Francois Fillon, Nicolas Sarkozy's campaign director, to celebrate the start of producing electricity with HDR-EGS
deep geothermal reservoir heat source
|
June 2008 |