Medium term circulation (35 l/s) / Power plant installation (1,5 MWe)



Installation of the geothermal loop
Foundation work performed by Fondasol for cementing job following
August 2007
Installation of the geothermal loop
Preparation of the platform to build the geothermal loop and the ORC power plant
September 2007
Installation of the geothermal loop
Reception of five Heat exchangers (Barriquand)
September 2007
Installation of the geothermal loop
Platform preparation (Company Leon)
October 2007
Installation of ORC power plant
Installation of the air cooling system (Turboden)
November 2007
Installation of ORC power plant
Installation asynchronous Generator 1,5MW
December 2007
Installation of ORC power plant
Installation radial turbine 1,5MW (Cryostar)
December 2007
Installation of geothermal loop
Air cooling system (Ormat)
January 2008
Installation of geothermal loop
Self-cleaning filter, (Poutet, Lefco, 50μm and 150μm)
February 2008
Installation of geothermal loop
Installing Pipes to connect heatexchanger with cooling system and wells (Stib Company)
April 2008
Installation of geothermal loop
Installation of actuators and sensors, automatisation (SOVEC)
Mai 2008
Installation of ORC power plant
Filling of Isobutane into ORC working fluid system
Mai 2008
Start of Production of electrical power
Visit of Francois Fillon, Nicolas Sarkozy's campaign director, to celebrate the start of producing electricity with HDR-EGS deep geothermal reservoir heat source
June 2008